Condo units at Aria On the Bay are still selling well as the building nears top off.

More than 80 percent of units are now in contract, a spokesman for the developer told the SFBJ. Construction has reached the 47th of 53 levels, with delivery projected in early 2018.

About two months ago, the developer had said 75 percent of units were in contract. Eight months ago, the number was at 70 percent. There are 648 units under construction, so each 5 percent increment is equal to another 32 units sold.