Foundation Pour Completed For 65-Story E11EVEN Hotel & Residences

Vertical construction is now officially underway at E11EVEN Hotel & Residences after a foundation pour was completed over the weekend.

The massive pour began Friday, June 23 at 7 p.m. and lasted a total of 16 hours.

A total of 70 cement trucks were rotated in and out of the project site to pour a combined 6,700 cubic yards of concrete.

Contractor John Moriarty & Associates oversaw the pour.

In early May, a tower crane was installed at the site.

On June 1, the developers announced that ground had been broken on a second 65-story tower, called E11EVEN Residences Beyond.

E11EVEN Hotel & Residences will have 449 residences, 36,852 square feet of commercial space, 2,049 square feet of office space, and four floors of parking garage.

E11EVEN Residences Beyond will have over 550 residential units, along with office, commercial, retail and parking.

E11EVEN Hotel & Residences is scheduled for completion in 2025, with E11EVEN Residences Beyond following in 2026.

 

 

15 Comments
most voted
newest oldest
Inline Feedbacks
View all comments
ray
2 months ago

2026 and 2027 seems more realistic for the towers. Seems like both towers are relatively simple architecturally. Simple but elegant in a NYC kind of way. 2025 might be doable for the first tower, however a year or two later is probable with rain, holidays and supply chain issues used as an excuse,

transplant
2 months ago

Huh? 2 years post foundation work is not unrealistic. It’s about the same timeline as Natiivo next door (started construction in February 2021 and will be completed by the end of this year)

SW30
2 months ago

Agreed. Last talk I had with the sales team, I was told the 1st tower would be completed 2026

Anonymous
2 months ago

Apart from 432 Park Avenue, which is considered one of the worst buildings built in NYC in recent years, most its billionaire skyscrapers are architecturally light years ahead of these proposed boxes.

Cover the Podiums
2 months ago

10/10 for the podium

anan
2 months ago

Moriarity is a heavy hitter as a GC so this should move along.

El Arqui
2 months ago

Best GC in town

Se me paro'
2 months ago

That is an aggressive completion date.

transplant
2 months ago

How so? 2 years post foundation work is pretty typical. It’s about the same timeline as Natiivo next door (started construction in February 2021 and will be completed by the end of this year)

Anonymous
2 months ago

By your own statements, you’re proving 2 years is agressive. Nativo, according to you, will take almost exactly 3 years.

Mad Dash
2 months ago

Will there be a skylounge?

anonymous
2 months ago

They needed extra concrete for the poles…

Anonymous
2 months ago

Now now, one would except this kind of development will make what’s left of the club scene in this area classier. Take that trash elsewhere.

ray
2 months ago

Maybe they could work out a deal with the Legacy developers to turn the live camera\feed
90 degrees to see this tower under construction. Of course after Legacy is further along.

Tom
2 months ago

Thank you urban developers, urban growth is great! Sprawl,on the other hand is bad….