Brightline has provided an update on construction activity to bond investors, dated July 20.
At MiamiCentral’s first phase (including the already open station), Joe & the Juice is now complete. Build out of a Parliament Coffee space is now 85% complete.
The second phase of MiamiCentral also continues to make progress:
- A permanent chiller is now fully installed and nearly operational – pending FPL completion
- Mechanical, electrical and plumbing rough-in installation is continuing
- On-going framing is being installed in Block A
- Precast V’s complete
- Close out of curtain wall on south side of Block A
- On-going framing being installed in Block A
- Terrazzo flooring being Poured
- Light fixtures being installed
On the actual rail line, a small amount of construction is also finishing up, with the focus being on completing Positive Train Control (needed for Tri-Rail). The start of field pre-testing for PTC from Miami to Overtown will begin this month.