The completion date for the massive Downtown Miami Signature Bridge and highway reconstruction project has been pushed back to late 2027, according to the project website.
The project budget remains listed at $840 million, as it was last year.
Last year, the project website listed a completion date of Summer 2026.
Before that, the completion date was listed as Fall 2023.
The contract began in October 2018, with a four-year deadline to the contractor for completion and a budget of $802 million. Extension of the deadline was permitted under certain circumstances, including weather and major events.
The project includes a rebuild of the intersection at I-95, the 836, and I-395 at the entrance to downtown Miami.
A Signature Bridge with multiple illuminated arches and a separate span of double-deck highway are among the many components of the project.
Preparation for pouring a second span of double-deck highway was underway last month, according to a March 8 stakeholder presentation.