Melo Group is nearing completion of their biggest project ever and has announced plans for their next tower. Downtown 5th,...
Two 52-story apartment towers that will bring thousands of residents into Miami’s urban core are nearing completion. The two towers...
Melo Group has announced big plans for downtown Miami. The developer told Diario Las Américas that they plan to build...
Downtown 5th second and final tower has topped off at 52 stories. The west tower topped off just 47 weeks...
The second 52-story tower at Downtown 5th is about to top off. Shell contractor L&R Structural Corp. wrote on Tuesday...
Melo Group has removed the first crane at their twin-tower Downtown 5th project after completing vertical construction on the first...
Melo Group’s Downtown 5th has now topped off – and the pace of construction has been blistering fast. It took...
Downtown 5th had a foundation pour this weekend for its West Tower. It is the second and final pour for...
Downtown 5th has had its first cranes installed. Last week, the Federal Aviation Administration granted approval for three tower cranes...
Developer Melo Group and its contractors reached a milestone this week at their twin-tower Downtown 5th construction project with one...
Crews at Downtown Miami’s twin 53-story tower Downtown 5th project are frantically preparing for a foundation pour, a new video...
Downtown 5th was given the green light by Miami officials last month, and documents obtained by The Next Miami show...
An application has been submitted to the Federal Aviation Administration to install tower cranes at the Downtown 5th construction site....
The twin Downtown 5th towers are now moving to the next phase of foundation work. Contractor L&R Structural Corp. wrote...
Melo Group has broken ground on one of the biggest projects ever in downtown Miami. Downtown 5th will include 1,042...