A foundation pour for the second, north tower at The Estates at Acqualina was completed July 12 and 13 in Sunny Isles.

Cemex USA said in a press release that it supplied concrete for the pour. The company said it expected to deliver an estimated 155,000 cubic yards of ready-mix concrete to the project site.

More than 275 Cemex workers and roughly 160 Cemex trucks recently supplied over 8,000 cubic yards of ready-mix for sub-contractor R&S Concrete, executing a continuous mat pour for the north tower’s foundation. Cemex supplied more than 9,000 cubic yards of concrete for the south tower’s foundation late last year and to date has provided more than 40,000 cubic yards for the overall project.

The $1.8 billion luxury condo project, developed by the Trump Group (no relation to the president) and built by general contractor Coastal Construction, will include two 50-story towers with a total of 247 units. The south tower will have 154 units, and the north tower will have 93 units. The project broke ground in May 2018 with unit sales beginning in 2015.

“A project like this where no expense has been spared to deliver an unrivaled luxury experience can obviously have their choice of suppliers,” said Jeff Bobolts, Cemex USA Regional President.

Condominiums at The Estates of Acqualina range in price from $4.2 million to $14 million, with the penthouses going for upwards of $35 million. Unit sizes range from 3,200 square feet to 5,600 square feet for the residences, and from 6,225 square feet to 10,000 square feet for the penthouses. The project will also include 50,000 square feet of amenity space.